Solution of steel pipe pile’s patching by graphic method
DOI:
CSTR:
Author:
Affiliation:

Clc Number:

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    In construction of a wharf located in the Yangtze River in Wuhan, a vertical pile at the front row near water deviated 1.4 m, the part of which above the mud course had to be cut off for the follow-up construction,and another steel pipe pile with the same geometric dimensions was supplemented on the same site. The calculation was rather difficult and we solved the problem by CAD graphical method, which was proved feasible in practice.

    Reference
    Related
    Cited by
Get Citation

栗志刚,徐柏松.用图解法求钢管桩的补桩方案[J].水运工程,2012,(8):35-37