阳光岛海域冲淤变化对LNG码头工程的影响分析*
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:

中交第一航务工程勘察设计院有限公司2025年科研课题项目(ZDIXM2025-25)


Analysis of seabed erosion and deposition changes in waters of Yangguang Island and their impact on LNG terminal project
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    洋口港阳光岛是国内重要的LNG接收港,通过对比不同时期的水下地形数据,分析阳光岛海域滩槽演变的长期动态变化、LNG码头区的冲淤情况以及对码头桩基的影响,并提出码头桩基的冲刷防护措施。结果表明,随着人工岛和码头配套设施的逐步建成,人工岛东北侧的大洪埂子逐年往西移动;北水道仍然维持西延、北移的趋势;中水道头部向西延伸减缓,有不断南压、拓宽的趋势。LNG码头区在不同阶段呈现出不同的冲淤模式,初期主要是微淤状态;2010年后,受码头建设影响,A1、B1码头周围出现显著冲刷;到2018年,码头区逐步转变为淤积状态,人工岛北侧岸坡的淤长影响明显增大。拟建A2码头工程将采用先期防护和后期防护(预留冲刷深度)相结合的方式,以减缓桩基的冲刷速度,延长桩基的使用年限。

    Abstract:

    Yangkou Port Yangguang Island is an important LNG receiving port in China,this paper analyzes the long-term dynamic changes of the tidal flat evolution,the erosion and deposition situation in the LNG terminal area,and the impact on the foundation piles of the terminal by comparing underwater topographic data from different periods.The results show that with the gradual completion of the artificial island and terminal supporting facilities,the Dahonggengzi sandbar on the northeast side of the artificial island has been moving westward year by year.The northern waterway continues to maintain a westward and northward extension trend.The head of the central waterway has slowed its westward extension,but shows a trend of continuous southward compression and widening.The LNG terminal area exhibits different patterns of erosion and deposition at different stages.In the early stage,it was mainly a micro-sedimentation state.After 2010,due to the impact of terminal construction,significant scour occurred around the A1 and B1 docks.By 2018,the terminal area gradually transitioned to a deposition state,and the sediment on the northern slope of the artificial island significantly increased.For the proposed A2 terminal project,a protection approach combining preliminary protection and post-construction protection with reserved scouring depth will be adopted to reduce the scouring rate of the pile foundation and prolong the service life of the pile foundation.

    参考文献
    相似文献
    引证文献
引用本文

曹豹杰.阳光岛海域冲淤变化对LNG码头工程的影响分析*[J].水运工程,2025(12):75-80.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2025-12-19
  • 出版日期:
文章二维码