疏浚土长距离管道输送技术在环保疏浚工程中的应用
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Application of long-distance-transport technology for dredging soil in the engineering of environmental dredging
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    滇池草海清淤工程疏浚区域分为3个片区,疏浚面积70万m2,工程量220万m3,输送距离8~15 km。针对输泥路径上的场地限制问题,进行了长距离输送方法的分析及研讨,结合施工现场实际情况,决定采用接力泵输送方法,实现了长距、高效输送疏浚土。

    Abstract:

    The construction area of environmental dredging engineering in Caohai of Dianchi Lake can be divided into three parts.The construction area is 700,000 square meters,the volume of work is 2.2 million cubic meters,and the transport distance is from 8 km to 15 km.In order to solve the problem of the limitation on the roadway,the long distance transport technology has been analyzed and discussed.On the basis of the practical problem of the construction site,the boost pumping is chosen which is efficient for long distance dredging soil transportation.

    参考文献
    相似文献
    引证文献
引用本文

吴 鹏,王 刚.疏浚土长距离管道输送技术在环保疏浚工程中的应用[J].水运工程,2017(S2):33-35.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2017-07-17
  • 出版日期:
文章二维码