富春江船闸改造工程消能区围堰水力原型观测与研究
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Observation of the hydraulic prototype in the energy dissipation zone cofferdam of the Fuchunjiang ship lock expansion and renovation project
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    富春江船闸扩建改造工程在运行水电枢纽工况下进行,施工围堰在地质条件复杂的泄洪区内,防渗技术难度大。对已完工程围堰防渗施工及处理方法进行介绍,通过对过流围堰的原型观测,获得了迎水面水流流速、冲击压力、脉动荷载等水力参数。

    Abstract:

    Fuchunjiang ship lock expansion and renovation project is carried out under the working condition of the hydropower hinge.Due to the complex geological conditions of the flood discharge area,there are great difficulties in seepage control technology.This paper introduces the control construction and treatment methods of the completed cofferdam seepage.Positive side flow velocity,impact pressure,pulsating loads and other hydraulic parameters are collected through prototype observation of overcurrent cofferdam.

    参考文献
    相似文献
    引证文献
引用本文

楼伟中,王恕,刘传新,等.富春江船闸改造工程消能区围堰水力原型观测与研究[J].水运工程,2017(2):106-109.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2017-02-19
  • 出版日期:
文章二维码