Reinforcement design and control measures during construction of landslide-revetmen
Author:
Affiliation:

Guangzhou Branch, CCCC Second Harbor Consultants Co., Ltd., Guangzhou 511442, China

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    舟山中远船务1#位护岸滑坡后土体处于不稳定状态,为重建此护岸,除了设计方案加以考虑外,施工中通过对可能产生的各种不利影响因素进行分析,以护岸实时监测数据为依据,采取了各种减小对护岸稳定安全影响的有效控制措施,保障了施工期护岸的稳定性。

    Abstract:

    In order to reinforce the landslide-revetment of Zhoushan COSCO Shipyard No.1 berth which is in an unstable state, not only the design schedule is taken into consideration, but also the probablely adverse influential factors are analyzed. To ensure the stability of revetment during construction period, various available control measures are taken based on real-time monitoring data.

    参考文献
    相似文献
    引证文献
引用本文

杨璧榕,李 丹.滑坡失稳护岸的加固设计与施工控制措施[J].水运工程,2012(5):152-156.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2012-06-19
  • 出版日期:
文章二维码