Abstract:To address the conflict between traditional curing periods and construction schedule for silane impregnation in LNG water intake caissons,this study carried out on-site graded zone tests at the Yingkou LNG project to systematically investigate the coupling relationship between initial physical properties of concrete(temperature difference,daily temperature variation,moisture content,strength)at curing ages of 7 d,10 d,14 d,and 21 d and its post-impregnation protective performance,following a dual validation approach of “initial conditions→performance verification”.Results demonstrate that at the curing age of 14 d,the temperature difference is 16.9 ℃,daily temperature variation is 1.7 ℃/day,surface moisture content is 5.2%,and compressive strength reached 42.2 MPa,all meeting regulatory standards.Post-impregnation permeation depth is 3.6 mm,with water absorption and chloride uptake reduced by 92.5% and 93.1% respectively,while protective performance meets specifications and is basically equivalent to that of the 28 d control group.This confirms the engineering feasibility of optimizing curing time to 14 d,enabling a reduction in critical construction duration from 44 d to 24 d(a reduction of 45.5%).While guaranteeing anti-corrosion quality,this scheme avoids winter construction risks and cuts the comprehensive project cost by approximately 7.5 million yuan.The study demonstrates that shifting silane impregnation decision-making from “age-dependent fixation” to “parameter-driven guidance” is feasible,providing a scientific basis for durability-oriented construction in time-sensitive water transport projects.